5 Outputs Of Control Cost For Projects

In my previous articles , I have talked about some of the tools and techniques that you need to know when planning to control costs for projects. In this article, I want to look at some of the outputs of controlling costs for projects. Follow me as we look at that on this article.

 

Now the outputs…

#1 Work Performance Information

Work Performance Information includes information on how the project work is performing compared to the cost baseline for the project. Variance in the work performed and the cost of the work is evaluated at the work package level and control account level. 

 

For projects using Earned Value Analysis, CPI, CV, EAC, VAC and TCPI are documented for inclusion in work performance reports for the project.

Control cost for projects

READ MORE

Share on Google Plus

About crmnigeria

0 comments:

Post a comment



First and Foremost we love to hear from you after you have gone through our articles.

You can comment as Anonymous if you don't have a Google Account. There are also other options apart from Gmail Accounts.

We are also not going to approve any comment that does not relate to what we are discussing on this blog.


Once again, Thanks for visiting our blog.